Trading Alert, Technical Alert
MIAX Pearl Equities
September 04, 2026 | 11:59 AM
MIAX Pearl Equities Exchange - Planned Network Switch Hardware Refresh for CH4 (Disaster Recovery) Edge Switches and Mandatory Testing
On Friday, September 25, 2026, the MIAX Pearl Equities Exchange will refresh customer facing CH4 (Disaster Recovery) extranet edge switches after the close of trading from 8:30 p.m. to 10:30 p.m. ET.
All MIAX Pearl Equities Exchange CH4 extranet edge switches will be replaced one-to-one with an updated model and all firm Cross Connects (CCs) will be moved to the same ports on the new switches. There are no changes required by firms for this hardware upgrade.
Following the upgrade, firms are required to verify all Pearl Equities Exchange cross connects, market data feeds and application logins.
Please note: This testing is scheduled to coincide with the 2026 SIFMA pre-testing date to minimize operational disruptions.
Details on testing and verifications:
- Testing will be held on Saturday, September 26, 2026, from 8:00 a.m. to 12:00 noon ET.
- Firms are required to perform the following verifications:
- Verify light levels and IP routing.
- Verify all 10G ULL and 1G LL CCs by logging into each subscribed application for each CC (i.e. establish application-level socket connections to MEO, FOI, FXD, etc., for all ports, across all CCs) and verify the login.
- Confirm heartbeat receipt for both the A & B market data feeds for all subscribed multicast feeds across each CC.
- After verifying connectivity, firms must email MIAX Trading Operations at TradingOperations@miaxglobal.com.